Outline planning permission
The broad principle of development at Harbour Yard has already been agreed.
PlanningProject programme
Follow the anticipated milestones for feedback, planning, construction and the first new homes at Harbour Yard.
The broad principle of development at Harbour Yard has already been agreed.
PlanningThursday 25 June, 3pm to 8pm at M Shed, Market Place, Bristol BS1 3HG.
ConsultationPlease submit comments by Friday 24 July 2026.
ConsultationPublic consultation for phase 2 completed in September 2026.
ConsultationPhase 2 Reserved Matters application submission is expected in Winter 2026.
ApplicationReserved Matters planning permission is expected in Summer 2027.
PlanningValidation and statutory consultation are expected in Summer 2027.
PlanningConstruction is expected to commence in Winter 2027.
DeliveryFirst occupations are indicated for Spring 2029, with overall completion in 2029.
DeliveryOverall completion is expected in 2029.